Two floorplans use the same netlist and timing constraints:
Metric | Floorplan P | Floorplan Q |
|---|---|---|
Estimated total wirelength | Lower | Higher |
Critical macro-to-register distance | Longer | Shorter |
Congestion near critical macro pins | Higher | Lower |
Floorplan Q achieves better setup timing after routing.
What is the strongest explanation?
Total wirelength combines critical and noncritical nets. A floorplan can reduce aggregate wirelength while making its most timing-sensitive connections longer or more congested. Timing-aware floorplanning must consider which connections are being improved.